Structural review of the design of the Douglas Reservoir 1B which was done internally by Townsville Water and was based on the existing reservoir Douglas 1A.
The work included:
- Review of structural design and compliance with the relevant standards.
- Check and suggestion for possible improvements, particularly of rafter and the amount of columns.
- Design of access hatch, ladder and manhole openings.
- Review and completion of tender specifications for steelwork / fabricated steelworks, concrete, painting and earthworks.